After bringing down the historic University of Oregon Hayward Field complex. The new world class Hayward Field Track and Field facility took it’s place just in time for the 2021 Summer Trials.
Owner: University of Oregon
General Contractor: Hoffman Construction
Start Date: 02-04-2019
Completion Date: 05-23-2020
Materials Used on Project and Quantities:
- 125K yards of Excavation
- 115K tons of Base Rock
RiverBend Construction Inc (a paving division within our company) paved the track in Jan 2020, which posed its own number of hurdles The surfacing contractor (Beynon Sports) said it was the 2nd smoothest track they have ever worked on.