Delta Highway March 12, 2021

Cold Plane to remove 2” of existing Asphalt, Replace with 2” of new L-3-1/2” Asphalt
New Striping

Forest Ridge

Project Description (3-5 sentences): This is a new 33 lot subdivision located in Dallas Oregon. This is the first of 3 phases. This subdivision is out in the country but minutes from downtown and all school in Dallas.

Amazon Corporation

Paving operations for a new distribution warehouse that was constructed for Amazon in Salem, OR. The paving area was just over 1 million square feet (23.1 acres). The paving operations included a variety of applications, which included semi-trailer parking areas, access roadways and large parking areas. The weather was unseasonably warmer than normal, which allowed us to place over 9000 tons in the month of January. The remainder, 17800 tons, was placed during March to May.